Georgia lien waiver requirements
Georgia prescribes two lien-and-payment-bond waiver forms: one for interim payment and one for final payment. Each must substantially follow O.C.G.A. § 44-14-366, use at least 12-point type, contain the mandatory statutory notice, and include the claimant's signature/seal, a witness signature with the (ADDRESS) line beneath it, and the execution date. The waiver itself is not notarized; a nonpayment affidavit is. Statute: O.C.G.A. §44-14-366(d)-(f).
Georgia at a glance
- Yes — O.C.G.A. §44-14-366
- Interim · FinalWhat the waiver types mean →
- No: a witness signs instead, then it's uploadedNotarization by state →
- The form prints a 90-day nonpayment notice
- Signed and witnessed upload, then GC review
By hand vs. with SubLien
Form, upload link, reminders and review in one place.
By hand
- Find the current Georgia form
- Fill it in Word or a PDF editor
- Save it as a PDF and email it to the sub
- The sub prints it, signs in front of a witness and scans it back
- Chase the sub by email
- Check the signed copy and file it against the pay application
With SubLien
- Pick the sub and the payment, or let a Procore pay app or QuickBooks bill start the draft
- SubLien fills in its Georgia form; you review and send
- The sub downloads the filled form from the email link, no account needed
- They sign it in front of a witness and upload it from the same link
- Up to three reminders go out on their own
- SubLien tracks it and your team reviews the upload, filed next to their COI and W-9
In SubLien, the Georgia form is signed in front of a witness and uploaded for your team's review. Every plan includes unlimited lien waivers for your included vendors. See pricing
Georgia lien waiver questions
Does Georgia require a specific lien-waiver form?
Yes. Section 44-14-366 prescribes an interim-payment form and a final-payment form. The selected form must substantially follow the statute, be at least 12-point type, and include its mandatory notice.
Can a subcontract require lien waivers for all future work?
Not as an advance waiver of lien or labor/material bond rights. A waiver made before the claimant furnishes the relevant labor, services, or materials is void.
Is the waiver ineffective until the check clears?
Not necessarily. Actual receipt of the stated funds is one trigger, but a separate written full-payment acknowledgment is another, and 90 days after execution is a third unless a timely affidavit of nonpayment was recorded. The statute does not define every check, ACH, reversal, or partial-payment scenario or settle disputed payments, so keep proof of collected funds.
Must a Georgia waiver be signed, witnessed, or notarized?
The statutory waiver has claimant signature/seal, witness, date, and address fields and no notary block. The claimant and witness should sign the same final form. The statutory nonpayment affidavit is different: it must be sworn, witnessed, notarized, and recorded.
Is the rule different on a public project?
The form rule still matters because § 44-14-366 expressly covers labor/material payment-bond rights. But public-work entitlement, notice, and suit procedures arise under separate statutes—Title 13 for state work, Title 36 for local work, and potentially Title 32 for transportation work.
Is the free Georgia PDF one I can use?
The free PDF is the text of public law with the blanks left blank, for your review. Your organization decides whether it fits the transaction; SubLien does not determine that a form is legally correct.
Full Georgia rules, sources and sample
What Georgia actually changes
Research summary
- Forms: Two prescribed forms—interim and final—not a four-form suite.
- Advance waiver: Void before the claimant furnishes labor, services, or materials; statutory subordination and dispute-settlement exceptions remain.
- Effect: Conclusive at actual receipt, separate acknowledgment of full payment, or day 90 absent a timely nonpayment affidavit.
- Scope: Releases lien and labor/material bond rights only, not other contract or debt remedies.
- Formalities: At least 12-point type, mandatory notice, claimant signature/seal, witness, execution date, and address; no waiver notary.
- Nonpayment: Record the sworn, witnessed, notarized affidavit before expiration and complete statutory service within seven days.
- Public work: Treat the form as a payment-bond release and separately track the applicable state, local, or Title 32 regime.
State-specific workflow notes
A claimant cannot waive lien or bond rights before furnishing labor, services, or materials. After work is furnished, a properly executed waiver becomes conclusive for the stated lien and bond rights at the earliest of actual receipt of the stated funds, a separate written acknowledgment of full payment, or 90 days after execution. An unpaid claimant prevents the 90-day result only by recording the statutory affidavit of nonpayment before the period expires, then serving it as required within seven days. A claim of lien alone is not a substitute.
Current Georgia law preserves the claimant's other contract and debt remedies. On public work, the same form can release payment-bond rights, so the GC should first identify the public owner, governing bond statute, bond, notice of commencement, claimant tier, and separate notice and suit deadlines. Use the statutory interim or final text, never a generic four-form template, never backdate, and resolve project-specific questions before sending.
How SubLien handles it now
SubLien prepares Georgia's interim or final form, then routes completion through a signed-and-witnessed upload. The GC reviews the returned document inside SubLien for the matching request, claimant signature and date, readable pages, witness signature, and witness identity and address. A correction request keeps the prior attempt and lets the signer upload a replacement.
Rules that change the workflow
1. Georgia's labels can mislead a four-form system
The statute supplies only a waiver and release of lien and payment bond rights upon interim payment and a waiver and release of lien and payment bond rights upon final payment. Both contain a mandatory notice explaining the 90-day consequence. A generic conditional-progress, unconditional-progress, conditional-final, or unconditional-final form should not be substituted merely because another state uses those labels.
2. Scope is deliberately narrow
Current § 44-14-366(a) limits the statutory release to lien and labor/material payment-bond rights. It does not waive other rights or remedies, such as an underlying contract claim. That limitation was added in response to the former statute's broader debt-extinguishment result and applies to waivers executed on or after January 1, 2021.
3. No advance waiver — but advance subordination is different
A claimant cannot waive lien or bond rights before furnishing labor, services, or materials. Section 44-14-366(f), however, expressly leaves an agreement to subordinate lien rights enforceable even if made before performance or payment. It also leaves room for settling a bona fide dispute concerning labor, services, or materials already furnished. Intake should distinguish waiver, subordination, settlement, and release of an already recorded instrument.
4. A nominally payment-based form can mature without payment
The waiver becomes conclusive at the earliest statutory trigger:
- actual receipt of the funds stated in the waiver;
- the claimant's separate written acknowledgment of payment in full; or
- 90 days after execution, unless the claimant records a substantially compliant affidavit of nonpayment before that period expires.
There is no separate statutory consideration formula. Because the third trigger does not depend on payment, the forms should not be described simply as conditional until paid.
5. Only the nonpayment affidavit stops the 90-day result
Before the 90-day period expires, an unpaid claimant must record the prescribed affidavit in the county where the property is located. Recording a claim of lien alone does not perform that function under current law. Within seven days after filing, the claimant must send a copy by registered or certified mail or statutory overnight delivery to the owner. If the claimant lacks privity with the owner and a notice of commencement was filed, the contractor must also receive a copy at the notice address. A timely affidavit suspends the waiver until full payment; it does not extend or shorten the separate deadline to record a claim of lien.
6. Form and signing details matter
- Use at least 12-point type. Boldface and all-capital type are not required.
- Include the statutory notice. The statute makes a form without that notice invalid and unenforceable.
- Complete the contractor, work, project, location, owner, property description, amount, through-date, execution date, signature/seal, witness, and address fields. An interim form expressly excepts stated retainage; the final form has no parallel retainage carveout.
- Upon the interim payment, lien priority—except as to retention—thereafter runs from the day after the through-date stated in the interim form.
- Incorrect field information does not automatically invalidate a form if its subject matter remains reasonably determinable. That savings rule is not permission to omit required text or execution.
- Do not backdate. Bibler treated the date shown on the form as controlling even when a later signature or delivery date was alleged.
- The waiver itself has a witness line but no notary block. The statutory affidavit of nonpayment requires the claimant's sworn signature, a witness, and a notary.
7. Electronic execution is qualified, not automatic
Georgia's UETA generally gives an electronic signature the same legal effect as a manual signature when the parties agreed to transact electronically. It does not displace § 44-14-366's substantive form, notice, witness, date, seal-line, or recordability requirements. An electronic workflow should capture affirmative e-transaction consent, separately attributable claimant and witness signatures, the exact rendered document, tamper-evident timestamps, and a durable audit record. SubLien's Georgia workflow does not witness electronically: the claimant and the witness sign the returned form on paper, and the signed copy is uploaded for the GC's review.
8. Private and public projects require different rights mapping
On a private project, the relevant security right is ordinarily the real-property lien, with any applicable payment-bond claim tracked separately. State and local public-work statutes instead establish payment-bond remedies: O.C.G.A. §§ 13-10-60 through 13-10-65 for state work (expressly excepting matters governed by Title 32) and §§ 36-91-90 through 36-91-95 for local work. The § 44-14-366 forms expressly reach labor/material bond rights, so a public-job waiver is not harmless merely because no private-property lien is being released. Identify the public owner, governing statute, bond, notice of commencement, claimant tier, notices, and bond-action deadline before requesting a waiver. Transportation work under Title 32 needs a separate analysis.
9. Qualified GC workflow
- Classify the job. Confirm private, state, local, or Title 32 work; identify the owner, contracting chain, property county, payment bond, notice of commencement, and claimant tier.
- Match the payment event. Use the statutory interim form only for a progress payment and the statutory final form only when final lien/bond-right release is intended. Do not request a waiver for future work.
- Generate without altering the legal core. Keep the statutory language, mandatory notice, 12-point minimum, signature/seal and witness lines, and all project/payment fields. Put the last furnished-through date and any retained amount in the proper interim fields.
- Execute and link evidence. Obtain the claimant and witness signatures, preserve the exact signed document and audit trail, and link it to the payment record and proof of actual receipt. Notarize only when the instrument calls for it; the waiver does not, while the nonpayment affidavit does.
- Calendar from the face date. Start a conservative 90-day control from the execution date printed on the waiver. Do not reset it based on delivery, check issue, or internal approval dates.
- Act on nonpayment promptly. If the claimant reports nonpayment, the claimant—not the GC—decides whether to record the statutory affidavit of nonpayment before the 90-day period expires, and then completes the seven-day service. Suspend operational reliance when a timely affidavit is identified.
- Close the record deliberately. After full payment following an affidavit, obtain the claimant's recordable affidavit of full payment upon request and record it in the same county. Handle any recorded claim of lien through its separate cancellation/release process.
Primary sources
- Official Georgia Code public portal — The Georgia Code Revision Commission makes the current Code available here on behalf of the Georgia General Assembly. Search O.C.G.A. § 44-14-366 for the forms, advance-waiver rule, scope, effectiveness triggers, affidavit, seven-day service rule, and exceptions; §§ 10-12-3, 10-12-5, and 10-12-7 for electronic transactions; §§ 13-10-60 through 13-10-65 for state public works; and §§ 36-91-90 through 36-91-95 for local public works.
- 2020 Ga. Laws Act 576 (SB 315), signed act — Rewrote § 44-14-366 effective January 1, 2021: limited the release to lien and labor/material bond rights, revised both forms and their notice, required at least 12-point type, extended the automatic-effect period to 90 days, and made the affidavit of nonpayment the preservation filing.
- 2021 Ga. Laws Act 210 (SB 143), signed act — Corrected the entity-owner service sentence so it refers to sending the recorded affidavit, not the underlying lien.
- Bibler Masonry Contractors, Inc. v. J.T. Turner Construction Co., 340 Ga. App. 490 (2017), official opinion PDF — Under the predecessor version, enforced the form's claimant-and-witness signature requirements and held that the deadline ran from the date stated on the waiver, not alleged later signing or delivery. Use it only for the unchanged execution/date structure; the former 60-day rule was replaced by 90 days.
- Arco Design/Build, LLC v. Savannah Green I Owner, LLC, 364 Ga. App. 380 (2022), official opinion PDF — Applied the predecessor statute to a 2020 waiver and rejected reliance on judicial-emergency tolling for the nonpayment filing. The opinion also identifies the January 1, 2021 change limiting current waivers to lien and bond rights.
- Georgia Uniform Electronic Transactions Act, HB 126 (2009), official General Assembly PDF — Supplies the enacted text of O.C.G.A. §§ 10-12-3, 10-12-5, and 10-12-7: electronic records and signatures generally may satisfy writing and signature requirements when the parties agree to transact electronically, while other substantive requirements remain.
Source-by-source reference points
- O.C.G.A. § 44-14-366(a)–(c): narrow scope, advance-waiver prohibition, and exclusive statutory-form rule.
- O.C.G.A. § 44-14-366(d)–(e): interim and final forms, 12-point minimum, required fields, mandatory notice, and limited error-saving rule.
- O.C.G.A. § 44-14-366(f): preserved subordination, bona fide dispute settlement, and recorded-instrument exceptions.
- O.C.G.A. § 44-14-366(g): three effectiveness triggers, 90-day affidavit process, seven-day service, suspension, and full-payment affidavit.
- O.C.G.A. §§ 10-12-3, 10-12-5, 10-12-7: UETA scope, party agreement, and electronic writing/signature effect.
- O.C.G.A. §§ 13-10-60–65; 36-91-90–95: state and local public-work payment-bond regimes and their separate procedural deadlines.
How SubLien handles Georgia
SubLien fills known project fields in its current template for Georgia; your team reviews the draft and sends it.
Waiver types SubLien records for Georgia: Georgia Interim · Georgia Final
Configured Georgia progress-payment reference preview
Georgia questions, answered in full
Does Georgia require a specific lien-waiver form?
Yes. Section 44-14-366 prescribes an interim-payment form and a final-payment form. The selected form must substantially follow the statute, be at least 12-point type, and include its mandatory notice. A generic national form is not a safe substitute.
Can a subcontract require lien waivers for all future work?
Not as an advance waiver of lien or labor/material bond rights. A waiver made before the claimant furnishes the relevant labor, services, or materials is void. An advance lien subordination agreement and a settlement of a bona fide dispute over already furnished work are separately preserved.
Must a Georgia waiver be signed, witnessed, or notarized?
The statutory waiver has claimant signature/seal, witness, date, and address fields and no notary block. The claimant and witness should sign the same final form. The statutory nonpayment affidavit is different: it must be sworn, witnessed, notarized, and recorded. For electronic signing, obtain consent and preserve separately attributable claimant and witness actions.
Is the rule different on a public project?
The form rule still matters because § 44-14-366 expressly covers labor/material payment-bond rights. But public-work entitlement, notice, and suit procedures arise under separate statutes—Title 13 for state work, Title 36 for local work, and potentially Title 32 for transportation work. Confirm the owner and bond regime before presenting any release.
How is a completed Georgia waiver reviewed in SubLien?
The signer uploads the signed-and-witnessed document. The GC checks the request details, claimant execution, readable pages, witness signature, and witness identity and address before approval; a rejected attempt remains in the history while a corrected copy is requested.