Montana lien waiver requirements
Montana does not prescribe statewide forms for ordinary private payment-stage lien waivers. It does impose a decisive timing rule: Mont. Code Ann. § 28-2-723 bars a construction contract from requiring a contractor, subcontractor, or material supplier to waive construction-lien or payment-bond rights before that claimant has been paid for the covered labor or materials. A GC should avoid terms demanding an operative prepayment release. A conditional document can make effect depend on the identified payment. An unconditional document directly releases its stated scope and should warn the claimant not to sign before payment.
What Montana actually changes
At a glance
- Prescribed routine form: No statewide private conditional/unconditional progress/final waiver set. The four SubLien variants are product-authored, not Montana forms.
- Advance waiver: Section 28-2-723 prohibits construction-contract requirements that make a claimant waive construction-lien or payment-bond rights before payment for its covered labor/materials.
- Payment/effectiveness: The statute does not define “paid” or a universal trigger. Tie a conditional document to one identified payment; use a direct-release unconditional document with a warning not to sign before payment. Keep normal GC payment records without an extra receipt or evidence workflow.
- Signature/notary/timing: No statutory notary or universal signing deadline for an ordinary waiver; agreed e-signatures generally work. Separate recorded and agency instruments have their own formalities and acceptance rules.
- Recorded rights: A paid preliminary-notice filer must use § 71-3-538; a satisfied actual lien uses §§71-3-537 and 71-1-211. A draw waiver does not complete either county process.
- Private/public/bond split: Private liens may shift to a 1.5-times substitution bond; public work uses Title 18 security and notices; State A&E uses Forms 116/106 and surety closeout.
- GC workflow: Classify first, match each document to its claimant and scope, and complete any recorder, bond, surety, or agency task separately. Do not add a payment rail, receipt checkbox, or proof upload to the ordinary waiver flow.
Detailed state rules and primary sources
State-specific workflow notes
Montana does not prescribe statewide forms for ordinary private payment-stage lien waivers. It does impose a decisive timing rule: Mont. Code Ann. § 28-2-723 bars a construction contract from requiring a contractor, subcontractor, or material supplier to waive construction-lien or payment-bond rights before that claimant has been paid for the covered labor or materials. A GC should avoid terms demanding an operative prepayment release. A conditional document can make effect depend on the identified payment. An unconditional document directly releases its stated scope and should warn the claimant not to sign before payment.
For each draw, match the claimant, project, amount, through-date, exceptions, and payer. Reconcile lower-tier releases only when the contract requires them. The Montana Supreme Court's Kratzer decision enforced a clear lower-tier-release condition, but it did not authorize demanding the unpaid claimant's own waiver. SubLien adds no payment rail, receipt confirmation, evidence reference, or proof upload. The GC keeps its normal payment records for any dispute.
Ordinary private payment-stage waivers have no statutory notary block. Agreed, attributable electronic signatures are generally recognized under Montana UETA. Separate instruments require separate handling: release a paid preliminary notice under § 71-3-538, and acknowledge a satisfied recorded lien under § 71-3-537 using mortgage-recording formalities.
Public work follows payment-security and agency documents, not a private property-lien form. State A&E projects use Form 116 for progress releases and notarized Form 106 at final closeout.
Rules that change the workflow
1. No statewide routine form, but Montana is not a generic no-law state
No reviewed MCA provision publishes conditional-progress, unconditional-progress, conditional-final, or unconditional-final text for ordinary private draw administration. There is no universal routine-waiver title, font, warning, witness block, acknowledgment, or notary mandate. SubLien may offer customer-and-counsel-reviewed forms, but they should be labeled SubLien-authored and nonstatutory, not routed as if Montana supplied no distinctive waiver law.
Montana does prescribe content for other instruments: the preliminary notice in § 71-3-532, the construction-lien claim in § 71-3-536, the release of preliminary notice in § 71-3-538, and the public-security claim notice in § 18-2-204. Those instruments serve different purposes and must not be presented as payment-stage lien-waiver forms.
2. Contractual advance-waiver requirements are prohibited
Section 28-2-723 reaches both construction liens and payment-bond claims. A construction contract cannot require the contractor, subcontractor, or material supplier to surrender either right before that same claimant has been paid for its furnished labor or materials. The rule applies by claimant and covered work; payment to an upstream party is not stated to be payment to a downstream claimant.
The statute does not say all future-right waivers are valid after payment, define whether partial payment supports a proportional or through-date release, define collected funds, publish a warning, or specify a remedy in the section. It also speaks to provisions in a construction contract. The official primary sources reviewed do not squarely decide whether a separately requested, genuinely conditional document executed before payment violates the statute when no release becomes operative until payment. State A&E Form 116 uses that conditional structure. Montana counsel should approve the exact clause and exchange mechanics.
An unconditional form before payment is the clear product risk. A contract workflow that requires it would contradict § 28-2-723 even if a template declares itself effective when unpaid. A safe GC workflow does not make the claimant sign a presently effective own-right release as the price of receiving money.
3. Payment, effectiveness, amount, and scope must match
Montana does not provide a universal statutory rule that every routine waiver takes effect on signature, check delivery, check clearance, ACH settlement, or payment allocation. The controlling anti-advance rule uses “paid” without defining that event in § 28-2-723. Consequently:
- A conditional document should identify the payer, claimant, amount, pay application or invoice, project, property, and covered through-date. Its effect should depend on the identified payment and should fail if that payment is not made.
- An unconditional document should directly release the identified scope and warn the claimant not to sign before payment. SubLien does not need a receipt confirmation, payment-method question, evidence reference, or proof upload; the GC keeps its ordinary payment records.
- A partial payment should produce no broader release than the reviewed consideration and agreed scope. Retainage, disputed amounts, pending or unapproved changes, future work, and other claims should remain reserved unless intentionally resolved.
- Final does not mean limitless. A final release should still identify the work cutoff, contract/payment application, amount, exceptions, and any rights outside construction liens. It should not contain a false lower-tier-paid or paid-in-full recital.
The prompt-payment statute permits written, itemized disapproval for failure to supply lien releases required by material contract documents and permits withholding only enough for the stated claim. It also requires the GC to pay a subcontractor within seven days after the GC receives owner or State payment, subject to the statute and subcontract. Those payment rules do not override § 28-2-723's prohibition on requiring that unpaid claimant's own operative waiver.
4. Lower-tier releases are real GC workflow, but claimant identity matters
In Kratzer, a public-school-project subcontract made the subcontractor's delivery of releases from its subcontractors and suppliers a condition precedent to the GC's final payment. The Montana Supreme Court enforced the unambiguous condition and held that the GC's unsuccessful proposal for the subcontractor's own general release did not waive or replace it. The decision is important operational evidence, not a holding that an unpaid claimant can be required to release its own lien or bond rights.
The practical distinction is:
- A GC may reconcile releases from lower tiers whose covered invoices have been paid, if the incorporated contract requires them and the forms comply with § 28-2-723.
- The GC should not treat an upstream claimant's warranty as proof that each independent lower-tier right was released.
- Each release should identify its claimant, covered work, payment, and exceptions. The GC should compare it with the lower-tier ledger and contract condition before withholding payment.
- A disputed own-right general release belongs in a separately negotiated settlement lane, not the routine pay-application lane.
5. Routine waiver, preliminary-notice release, and recorded-lien satisfaction are three documents
- Routine payment-stage waiver: No statutory Montana form or notary requirement located. Its effect comes from the approved instrument and transaction facts, constrained by § 28-2-723.
- Release of preliminary notice: Section 71-3-538 applies only when a notice of right to claim a lien was filed. Once paid for the noticed services/materials, the filer must release it. A paid filer has five business days after the contracting owner's request. The county filing must include the preliminary notice's file number, filing date, and recipient and must be signed by the filer or authorized signer.
- Satisfaction of an actual lien: Section 71-3-537 applies when lien indebtedness is paid and satisfied. The creditor must acknowledge satisfaction in the same manner as a mortgage. Under § 71-1-211, that means a recordable certificate executed by the proper party, acknowledged or proved and certified, stating payment, satisfaction, or discharge, then recorded.
An ordinary signed SubLien PDF does not itself make either county filing, satisfy the acknowledgment requirement for a recorded lien, or prove that a recorder accepted the instrument.
6. A private lien may move to a substitution bond
After a construction lien is filed, § 71-3-551 lets the contracting owner, original contractor, or a subcontractor file a 1.5-times cash or approved corporate-surety bond before foreclosure begins or within 30 days after service of the foreclosure complaint. Section 71-3-552 then discharges the real-property lien and substitutes the bond; § 71-3-553 keeps the lien limitation period for the bond action.
This is distinct from a public payment bond. Once the private substitution bond exists, a property-only waiver is at best incomplete workflow information: the project record should identify the bond, principal, surety, court, amount, lien, complaint/service date, and whether the proposed release reaches or reserves the substituted-bond claim. Section 28-2-723 expressly names a “payment bond”; whether and how it applies to this different court-filed substitution bond should be resolved by Montana counsel.
7. Public work requires a payment-security and agency lane
Title 18 generally requires a public prime to provide performance and payment security protecting laborers, mechanics, subcontractors, and suppliers. A governmental entity may waive that security for projects under $150,000, and a school district may do so under $7,500; § 18-2-202 addresses government liability when required security is waived or omitted.
Public claim preservation is not handled by a private property-lien waiver:
- A covered claimant's § 18-2-204 signed claim notice must be presented and filed in the prescribed substance within 90 days after contract completion and affirmative acceptance by the public body.
- A supplier to a subcontractor must first give the prime the substantially prescribed § 18-2-206 notice personally or by certified mail within 30 days after first delivery. Other actual or constructive notice is insufficient under that section.
- Because § 28-2-723 covers payment-bond claims, a public-project contract cannot require the unpaid claimant to waive that right before payment.
- A generic form limited to a lien against the real property does not facially release a public payment-security claim, but the product must not imply that it completes public closeout or resolves all claimant rights.
State A&E projects add their own contractual documents. Form 116 is a two-part progress-release document: its conditional half identifies a check and waits for receipt, endorsement, and bank payment; its unconditional half recites progress payment and warns against signing unpaid. Form 106 is the final contractor affidavit/release, says listed lower-tier amounts will be paid from final payment, broadly releases claims to induce final payment, and includes a Montana notarial jurat. The General Conditions connect those forms to prior-payment release collection, surety consent, and final closeout. Other Montana public bodies may use different contracts and forms.
8. Signature, notary, timing, and electronic records
The construction-lien statutes impose no witness, acknowledgment, jurat, or notarization requirement on an ordinary private payment-stage waiver. Obtain the claimant's authorized signature, printed name, title, date, electronic-consent evidence, attributable act, exact version/hash, delivery record, and completed exceptions because authority and scope remain substantive issues.
Montana UETA generally recognizes an agreed, attributable electronic record/signature and permits electronic notarization when notarization is otherwise required and all required information is attached or logically associated. It does not make a routine waiver notarized, force a county recorder or State agency to accept an electronic instrument, or convert SubLien's evidence certificate into a notarial act. The recorded-lien satisfaction and Form 106 lanes therefore need explicit acknowledgment/notary and acceptance controls.
No statute reviewed sets a universal date by which a routine progress or final waiver must be signed. Timing instead comes from § 28-2-723, the document's stated payment condition, the contract/pay cycle, and separate filing rules. The five-business-day clock in § 71-3-538 belongs only to a paid preliminary-notice filer after owner request.
9. Practical qualified-GC workflow
- Classify the project and document. Record private or public ownership, awarding body/agency, State A&E status, claimant tier and hiring party, payment security, any preliminary notice, any filed lien, and any private substitution bond. Do not generate a routine waiver for a recorder, court, or bond-notice task.
- Validate the contract requirement. Confirm that any release condition is incorporated, claimant-specific, and consistent with § 28-2-723. Separate lower-tier releases already supported by payment from the current claimant's own rights. Escalate any presently effective prepayment or broad settlement release.
- Build one-draw facts. Reconcile pay application/invoice, schedule of values, covered through-date, amount, retainage, change orders, disputes, lower tiers, and payer/payee.
- Exchange conditionally. Use a Montana-labeled, nonstatutory conditional waiver whose operative event is the identified payment. Deliver funds without requiring the unpaid claimant's own unconditional waiver.
- Use an unconditional form for paid scope. Match its scope to the conditional document, preserve unresolved items, and retain the GC's ordinary payment records. Do not add a separate claimant-receipt or payment-proof step.
- Complete distinct release tasks. If a preliminary notice was filed, collect and file the § 71-3-538 release and receipt. If a construction lien was recorded, route an acknowledged satisfaction under §§71-3-537 and 71-1-211. If a substitution bond exists, preserve or settle the bond claim expressly.
- Run public closeout separately. Index the public security and statutory notice deadlines. For State A&E work, use the current agency Forms 116, 106, 103, and incorporated General Conditions; verify the agency's electronic-signing and delivery rules.
- Preserve the waiver record. Store the completed instrument, signer authority, hash/version, timestamps, delivery, exceptions, lower-tier reconciliation, and county/agency acceptance where applicable. The GC's ordinary payment records remain in its normal system; a SubLien evidence seal documents the waiver record, not legal sufficiency or payment.
Primary sources
Currency and coverage check
- https://mca.legmt.gov/bills/mca/index.html — Official Montana Legislature publication of the Montana Code Annotated 2025, the current codification available at the research cutoff. The cited section pages were checked on August 17, 2026.
- https://doa.mt.gov/ae/ — Current Montana Department of Administration Architecture & Engineering forms index, checked on August 17, 2026. It lists Forms 103, 106, 113, and 116 and the November 2023 General Conditions as current contractor documents.
- https://courts.mt.gov/Courts/Supreme/Summaries/archives — Official Montana Supreme Court opinion-summary archive, checked through the decisions available by the research cutoff.
Advance waiver and construction payment
- https://mca.legmt.gov/bills/mca/title_0280/chapter_0020/part_0070/section_0230/0280-0020-0070-0230.html — § 28-2-723: a construction contract may not require a contractor, subcontractor, or material supplier to waive a construction lien or payment-bond claim before payment for that claimant's furnished labor or materials.
- https://mca.legmt.gov/bills/mca/title_0280/chapter_0020/part_0210/sections_index.html — Official index to Montana's construction-payment part, including payment, interest, retainage, applicability, and alternative-billing provisions.
- https://mca.legmt.gov/bills/mca/title_0280/chapter_0020/part_0210/section_0030/0280-0020-0210-0030.html — § 28-2-2103: monthly pay requests; written and itemized disapproval; lien releases as possible material contract documents; approved owner payment within seven days; and downstream payment within seven days after receipt.
- https://mca.legmt.gov/bills/mca/title_0280/chapter_0020/part_0210/section_0100/0280-0020-0210-0100.html — § 28-2-2110: retainage generally may not exceed 5%, must be passed down without increase, and must be released for a separately priced portion after final acceptance of that portion.
- https://juddocumentservice.mt.gov/getDocByCTrackId?DocId=526792 — Kratzer v. Hardy Construction Co., 2025 MT 140, ¶¶13-23. The Court enforced an unambiguous subcontract condition requiring the subcontractor to provide releases from its own subcontractors and suppliers before final payment. It did not decide the validity of requiring the unpaid subcontractor's own lien waiver under § 28-2-723.
Private construction liens, notices, and releases
- https://mca.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/sections_index.html — Complete official index for Title 71, chapter 3, part 5, including lien creation, preliminary notice, claim filing, satisfaction, notice release, bond substitution, and enforcement.
- https://mca.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0210/0710-0030-0050-0210.html — § 71-3-521: construction liens against real estate for covered services or materials furnished under a real-estate-improvement contract.
- https://mca.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0310/0710-0030-0050-0310.html — § 71-3-531: who must give a notice of right to claim a lien, exemptions, 20- or 45-day delivery timing, filing within five business days after notice, and one-year duration.
- https://mca.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0320/0710-0030-0050-0320.html — § 71-3-532: prescribed content for the preliminary notice of right to claim a lien. This is not a payment-stage waiver.
- https://mca.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0350/0710-0030-0050-0350.html — § 71-3-535: construction-lien claim filing generally within 90 days after final furnishing or the owner's notice of completion.
- https://mca.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0360/0710-0030-0050-0360.html — § 71-3-536: substantially sufficient form and content for a filed construction-lien claim. This is not a payment-stage waiver.
- https://mca.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0370/0710-0030-0050-0370.html — § 71-3-537: after lien indebtedness is paid and satisfied, the creditor must acknowledge satisfaction in the same manner as a mortgage and is liable for injury and action costs caused by failure.
- https://mca.legmt.gov/bills/mca/title_0710/chapter_0010/part_0020/section_0110/0710-0010-0020-0110.html — § 71-1-211: the mortgage-satisfaction analogue requires an executed, acknowledged-or-proved, recordable certificate stating payment, satisfaction, or discharge, followed by recording.
- https://mca.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0380/0710-0030-0050-0380.html — § 71-3-538: a paid preliminary-notice filer must file a release; after the contracting owner's request, a paid filer has five business days. The filing must identify the original file number, date, and notice recipient and be signed by the filer or an authorized person.
- https://mca.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0510/0710-0030-0050-0510.html — § 71-3-551: owner, original contractor, or subcontractor may substitute a cash or approved surety bond equal to 1.5 times a filed lien before foreclosure or within 30 days after service of the complaint.
- https://mca.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0520/0710-0030-0050-0520.html — § 71-3-552: filing the qualifying bond discharges the lien against the real property and substitutes the bond.
- https://mca.legmt.gov/bills/mca/title_0710/chapter_0030/part_0050/section_0530/0710-0030-0050-0530.html — § 71-3-553: the claimant proceeds against the substituted bond within the same limitation period applicable to the lien.
Public-work payment security
- https://mca.legmt.gov/bills/mca/title_0180/chapter_0020/part_0020/sections_index.html — Official index to Montana's public performance, labor, and materials security provisions.
- https://mca.legmt.gov/bills/mca/title_0180/chapter_0020/part_0020/section_0010/0180-0020-0020-0010.html — § 18-2-201: covered public bodies generally require performance and payment security; governmental entities may waive it below $150,000, and school districts below $7,500.
- https://mca.legmt.gov/bills/mca/title_0180/chapter_0020/part_0020/section_0020/0180-0020-0020-0020.html — § 18-2-202: when government waives or fails to take required security, the government becomes liable to persons the security would have protected.
- https://mca.legmt.gov/bills/mca/title_0180/chapter_0020/part_0020/section_0040/0180-0020-0020-0040.html — § 18-2-204: covered claimants have a security action only after filing a signed notice in the prescribed substance within 90 days after contract completion and affirmative public acceptance.
- https://mca.legmt.gov/bills/mca/title_0180/chapter_0020/part_0020/section_0060/0180-0020-0020-0060.html — § 18-2-206: a supplier to a subcontractor must give the prime contractor a substantially compliant written security notice personally or by certified mail within 30 days after first delivery.
Electronic execution and official State A&E documents
- https://mca.legmt.gov/bills/mca/title_0300/chapter_0180/part_0010/section_0040/0300-0180-0010-0040.html — § 30-18-104: UETA applies only when each party agrees to transact electronically; agreement for one transaction does not compel another.
- https://mca.legmt.gov/bills/mca/title_0300/chapter_0180/part_0010/section_0060/0300-0180-0010-0060.html — § 30-18-106: records, signatures, and contracts are not denied effect solely because they are electronic; electronic form can satisfy writing and signature requirements.
- https://mca.legmt.gov/bills/mca/title_0300/chapter_0180/part_0010/section_0080/0300-0180-0010-0080.html — § 30-18-108: attribution depends on whether the electronic signature was the person's act, considered with context and circumstances.
- https://mca.legmt.gov/bills/mca/title_0300/chapter_0180/part_0010/section_0100/0300-0180-0010-0100.html — § 30-18-110: where another law requires notarization, acknowledgment, verification, or oath, the authorized person's electronic signature plus required information can satisfy it.
- https://mca.legmt.gov/bills/mca/title_0300/chapter_0180/part_0010/section_0170/0300-0180-0010-0170.html — § 30-18-117: each governmental agency decides whether and how it accepts electronic records and signatures; UETA does not compel agency acceptance.
- https://doa.mt.gov/_docs/ae/Forms/Const-Forms/Form-116-Lien-Release-Form.pdf — State A&E Form 116, Lien Release Form. Its conditional progress release depends on receipt, endorsement, and bank payment of the identified check; its unconditional progress release recites receipt and warns against signing before payment. Neither half has a notary block.
- https://doa.mt.gov/_docs/ae/Forms/Const-Forms/Form-106-Affidavit-of-Completion-Release-of-Liens.pdf — State A&E Form 106, Affidavit of Completion Release of Liens. The contractor makes final closeout representations, gives a broad final release to induce final payment, and signs before a Montana notary.
- https://doa.mt.gov/_docs/ae/Forms/Const-Forms/General-Conditions-November-2023.pdf — State A&E General Conditions §§2.1.3 and 9.10.2-.10. Progress releases may be required for work covered by prior progress payments; final payment requires Form 106, surety consent, and designated closeout materials. These are contract documents, not universal private-work statutes.
Source-by-source reference points
1. Montana classification
Title: State-specific anti-advance rule, no statewide routine form
Body: Montana does not prescribe four private payment-stage forms, but § 28-2-723 makes GENERIC legally incomplete. Label any product-authored form nonstatutory and expose the Montana rule before generation.
2. Contract and payment boundary
Title: Do not require the claimant's own operative waiver before payment Body: Match one conditional document to one claimant, payment, project, pay application, amount, and through-date. The unconditional document directly releases that scope and warns the claimant not to sign before payment; SubLien asks for no separate receipt or proof.
3. Lower-tier closeout
Title: Collect actual lower-tier releases when the contract requires them Body: Kratzer enforced a clear condition requiring releases from the subcontractor's own subcontractors and suppliers before final payment. It did not validate conditioning payment on the unpaid subcontractor's own presently effective waiver.
4. County-recorded instruments
Title: Preliminary-notice release and lien satisfaction are separate Body: A paid filer releases a preliminary notice under § 71-3-538, including required filing data and a five-business-day owner-request clock. A paid and satisfied lien needs acknowledged mortgage-style satisfaction and recording under §§71-3-537 and 71-1-211.
5. Bond rights
Title: Identify public security and private substitution bonds Body: Section 28-2-723 protects payment-bond claims from prepayment waiver. Title 18 public notices and a §§71-3-551-.553 private substitution-bond claim are distinct tracks; state expressly whether each bond right is reserved or released.
6. State A&E projects
Title: Use the agency's progress and final package Body: Current State A&E Form 116 handles progress releases; notarized Form 106, surety consent, and incorporated closeout documents govern final payment. These agency forms do not become universal private Montana forms.
The four waivers, and what each one says
Two questions decide which one you are sending: has the money actually arrived, and does this cover the whole job or just this pay period? These are the descriptions the industry uses — what a specific Montana document releases is a question for your counsel, on its own words.
Takes effect only when the stated payment is actually received. Covers work through a stated date or payment, and typically reserves retainage and later work.
States the release outright after payment. Same scope as the conditional partial — this pay period, not the whole job.
Same condition as above — effective on receipt of the stated payment — but scoped to the job through completion rather than to one period.
The release stated outright after final payment, for the job through completion. This is the one that is expensive to sign early, which is why the order it goes out in matters.
Where they land in a pay cycle
This is how the paperwork tends to move, not a rule about Montana. What your subcontracts require, and when, is your organization’s decision with counsel.
- 1Sub bills you
The pay application arrives for the period.
- 2Conditional goes out
Requested with or ahead of the payment.
- 3You pay
The payment is sent and the money arrives.
- 4Unconditional follows
Requested once the money has actually landed.
Final payment repeats the pattern at the end of the job. The step that goes wrong in practice is the fourth one: the conditional went out, the money arrived, and nobody went back for the unconditional.
Montana’s mechanics’ and construction lien provisions are at Mont. Code Ann. Title 71, Chapter 3, Part 5 (Construction Liens), §§ 71-3-521 to 71-3-564.
Read it on mca.legmt.govWhat Montana’s lien chapter covers
23 sections ↓
Section whose heading names a waiver or release: 71-3-538. That is a match on the heading text, not a statement about what those sections say.
- Scope
- Definitions
- Who may claim construction lien -- limitation
- Limitation of lien for materials supplied
- Extent of lien
- Amount of lien
- Notice of right to claim lien required -- exceptions
- Content of notice of right to claim lien
- Notice of completion
- Filing with county clerk -- notification of owner
- Attachment of lien -- filing
- Content of lien notice
- Acknowledgment of satisfaction of lien -- penalty
- 71-3-538 Release of notice of right to claim lien
- Priority among holders of construction liens
- Priority of construction liens as against claims other than construction lien claims
- Substitution of bond allowed -- filing -- amount -- condition
- Lien discharged upon filing of bond
- Action upon bond -- period of limitation same
- Parties
- Limitation on actions
- Rules of practice
- Arbitration of lien disputes
Conditional Partial · Unconditional Partial · Conditional Final · Unconditional Final
Montana lien waiver questions
Does Montana require a statutory lien-waiver form?
Not for ordinary private progress or final payment administration. Montana does not publish four conditional/unconditional variants. It does prescribe content or formalities for different documents, including preliminary notices, construction-lien claims, releases of preliminary notices, recorded-lien satisfaction, and public-security notices. A product-authored routine waiver should be labeled nonstatutory.
May a contract require a lien or bond waiver before payment?
No. Section 28-2-723 says a construction contract may not require a contractor, subcontractor, or material supplier to waive its construction-lien or payment-bond claim before it has been paid for its furnished labor or materials. The section does not squarely decide every separately exchanged conditional instrument. Use a document that becomes operative only with the identified payment and obtain Montana-counsel approval for the workflow.
When does a Montana waiver become effective, and must funds clear?
Montana does not prescribe a universal payment-stage trigger, and § 28-2-723 does not define “paid.” For ordinary private work, identify the payer, claimant, amount, covered work, and through-date. Make a conditional document depend on that payment; make an unconditional document a direct release with a warning not to sign before payment. SubLien asks for no payment rail, check number, receipt confirmation, evidence reference, or proof upload. The GC's ordinary payment records remain available for any dispute. State A&E Form 116's check-specific receipt, endorsement, and bank-payment trigger applies only in that agency workflow.
Must a waiver be notarized, and may it be electronically signed?
An ordinary private payment-stage waiver has no Montana statutory witness or notary requirement. Montana UETA generally recognizes agreed and attributable electronic records/signatures. Notarization or acknowledgment is required in separate lanes, including State A&E Form 106 and mortgage-style satisfaction of an actual lien. Government agencies and recorders control whether and how they accept electronic instruments.
Can one form handle private work, public work, bond rights, and a filed lien?
No qualified workflow should assume that. A routine private waiver, § 71-3-538 preliminary-notice release, §§71-3-537/71-1-211 lien satisfaction, private substitution-bond claim, Title 18 public-security claim, and State A&E closeout package are distinct. Classify the project and document, preserve notice deadlines, and state bond-right scope expressly before collecting any release.
Are the sample forms on this page ones I can use?
They are samples to review with your attorney, not a determination that either fits your transaction. The two PDFs offered here are plain conditional and unconditional waivers written by SubLien for giveaway; no state published them, and SubLien's reference as of 2026-08-31 identifies no prescribed Montana form they could be a copy of. Inside SubLien, the current internally source-reviewed system template is filled from your project record; SubLien does not determine that a form is legally correct.